Whole-Home Renovation

Multi-room remodel with cabinet, floor, paint, fixture, and systems work across the full footprint

Comprehensive whole-home renovation proposal covering multiple rooms, flooring replacement throughout, paint, kitchen and bath updates, and selective systems work. Designed for $150k–$600k residential projects.

Sections

10

Variables

13

Word count

~2200

Validity

30 days

Variables you'll fill in

{{client_name}}

Client namereq

e.g. Jane Homeowner

{{client_address}}

Project addressreq

e.g. 1234 Main St, Phoenix AZ 85001

{{contractor_name}}

Your company namereq

e.g. Acme Construction LLC

{{contractor_license}}

License numberreq

e.g. ROC 123456

{{scope_summary}}

One-paragraph scope summaryreq

e.g. Describe what this project covers in 2-3 sentences.

{{total}}

Total contract pricereq

e.g. 24500

{{deposit}}

Deposit / down paymentreq

e.g. 5000

{{start_date}}

Estimated start datereq

e.g. 2026-05-01

{{completion_date}}

Estimated substantial completionreq

e.g. 2026-06-15

{{proposal_date}}

Date of proposalreq

e.g. 2026-04-18

{{home_sqft}}

Total home square footagereq

e.g. 2800

{{rooms_in_scope}}

Rooms in scopereq

e.g. Kitchen, 2 baths, primary suite, living room, dining, hallway, laundry

{{occupancy_plan}}

Occupancy plan during work

e.g. Homeowners relocating off-site weeks 4-14; on-site for weeks 1-3 and 15+

Section-by-section preview

01Scope of Work

reqai rewritable

This proposal covers a whole-home renovation at {{client_address}}, approximately {{home_sqft}} square feet. Rooms in scope: {{rooms_in_scope}}. The work is phased to allow for predictable cash flow and minimize compounding delays.


Phase 1 — Pre-construction (Weeks 1–2)

Finalize selections for all rooms; submit cabinet, stone, tile, flooring, and appliance orders

Submit permit applications for mechanical, electrical, plumbing, and structural work

Set up site protection, staging, and dumpster


Phase 2 — Demolition & rough-in (Weeks 3–6)

Interior demo across all rooms in scope

Rough plumbing, electrical, and HVAC modifications; schedule rough inspections

Structural work: beam replacements, wall removals, subfloor repairs


Phase 3 — Shell & systems complete (Weeks 7–10)

Insulation, drywall, texture, prime

Paint ceilings and accent walls ready for trim

Window/door replacement if in scope


Phase 4 — Cabinets, stone, and tile (Weeks 11–15)

Kitchen and bath cabinets; countertop template and install

All tile work (floor, wall, showers, backsplashes)


Phase 5 — Finishes and trim (Weeks 16–18)

Finish flooring install throughout

Base, case, and crown trim; paint touch-ups

Light fixtures, plumbing trim, cabinet hardware, door hardware


Phase 6 — Appliance install, final inspections, punch (Weeks 19–20)

Appliance delivery and install; final HVAC commissioning

Coordinate and pass final AHJ inspections

Walk-through; punch list; final deep clean

02Schedule

reqai rewritable

Estimated duration: 20 weeks (5 months) from permit issuance to substantial completion. {{occupancy_plan}}


Start date on or about {{start_date}}; substantial completion targeted for {{completion_date}}.


**Weather and supply chain:** Exterior work (windows, roofing if included) is subject to weather. Appliance, cabinet, and stone lead times can add 2–6 weeks to the critical path and are not under contractor control. Schedule is re-baselined after Phase 2 when all rough conditions are known.

03Investment

req

Total contract price: {{total}}


Fixed-price with progress billing tied to physical completion, not calendar. Draws are as follows:


**Deposit: {{deposit}}** — at signing

**Rough complete: 20% of balance** — rough plumbing, electrical, HVAC, and structural work passed inspection

**Shell complete: 15%** — drywall, paint prep, pre-wire

**Cabinets set: 15%** — all cabinet runs installed and leveled

**Stone installed: 10%**

**Flooring complete: 10%**

**Substantial completion: remaining 30%** — includes final punch, certificate of occupancy or final inspection


Allowances are itemized separately and reconciled at closeout. Under-runs credit to {{client_name}}; over-runs (due to selected material exceeding allowance) billed by Change Order.

04Payment Terms

req

Each draw is invoiced upon achievement of the named milestone. Due within seven (7) business days. {{contractor_name}} provides conditional lien waivers upon receipt of each draw and unconditional waivers upon clearance of the payment.


Invoices are due upon receipt. Payments more than ten (10) calendar days past due accrue a service charge of one and one-half percent (1.5%) per month on the unpaid balance, or the maximum rate permitted by law, whichever is less. {{contractor_name}} reserves the right to stop work and preserve lien rights if any progress payment is not received within five (5) business days of the due date. All retained mechanic's lien, stop notice, and bond rights under applicable state law are preserved.

05Exclusions

reqai rewritable

The following items are specifically NOT included in the contract price and are the responsibility of {{client_name}} unless added by written Change Order:


Permits, plan-review fees, and jurisdictional inspection fees unless explicitly itemized above

Repair or remediation of pre-existing code violations discovered during the work

Asbestos, lead paint, mold, or other hazardous material abatement

Structural engineering, architectural drawings, or third-party design services

Finish selections, fixtures, or appliances not listed in the itemized scope

Work on concealed systems (electrical, plumbing, HVAC, framing) beyond the points of connection identified

Landscaping restoration beyond returning disturbed areas to rough grade

Post-completion cleaning beyond construction broom-clean

Roofing, siding, and exterior painting unless explicitly itemized

Landscaping, hardscaping, and site drainage

Third-party design fees (architect, interior designer, engineer)

Relocation costs for owners or pets during construction

Temporary housing, storage, or moving services

Asbestos/lead testing and abatement in pre-1978 homes

06Assumptions

reqai rewritable

This proposal is based on the following assumptions. If any assumption is incorrect, the contract price and schedule are subject to adjustment by Change Order:


Site access is available during normal working hours (7am–5pm, Monday–Saturday)

Adequate parking is available within 100 feet of the work area

Electrical power and potable water are available on-site at no cost to contractor

Existing structural elements, waste lines, water supply, and electrical service are in serviceable condition unless noted

{{client_name}} will remove personal property, artwork, and valuables from the work area prior to start

Work is based on a single mobilization; re-mobilization required due to delays outside contractor's control will be billed at current rates

All selections are confirmed in writing before Phase 2 begins; late selections push schedule day-for-day

Owner is reachable via email within 24 hours during construction for selection decisions and Change Order approval

Permit issuance within 4 weeks of application (AHJ-dependent; contractor is not responsible for AHJ delays)

07Change Order Process

req

Any modification to the scope, specifications, materials, or schedule set forth in this agreement must be authorized in writing as a Change Order signed by both parties before the work is performed. Each Change Order will describe the modified scope, any adjustment to the contract price, and any impact on the schedule. Verbal instructions do not modify this agreement. Additional time and cost associated with unforeseen conditions — including but not limited to concealed rot, asbestos, mold, faulty prior installation, unmarked utilities, or code-required upgrades triggered by the work — will be documented as a Change Order and billed at the rates stated in this proposal or at {{contractor_name}}'s then-current published labor rates, whichever is in effect at the time the condition is discovered.

08Warranty

reqai rewritable

{{contractor_name}} warrants the workmanship of the installed work for a period of one (1) year from the date of substantial completion. Manufacturer warranties on materials and equipment pass through to {{client_name}} as provided by the manufacturer and are the exclusive source of any material warranty. This warranty does not cover normal wear, abuse, neglect, acts of God, subsequent work performed by others, damage from settlement or movement of the building, or modifications to the installed work performed without written consent. To make a warranty claim, {{client_name}} must notify {{contractor_name}} in writing within thirty (30) days of discovering the alleged defect and allow reasonable access to inspect and repair.

09Validity & Acceptance

req

This proposal is valid for 30 days from the proposal date ({{proposal_date}}). Pricing is subject to change after that date due to material market fluctuations and scheduling availability. Acceptance requires signature below and receipt of the deposit amount stated in Payment Terms. Upon acceptance, this proposal, together with any attached specifications and subsequent written Change Orders, constitutes the complete agreement between the parties and supersedes any prior oral or written discussions.

10Signatures

req

**{{contractor_name}}** — License {{contractor_license}}


By: ________________________ Date: ______________


Print Name: ________________________



**{{client_name}}** — Owner / Authorized Representative


By: ________________________ Date: ______________


Print Name: ________________________


Property Address: {{client_address}}

Default payment terms

50% deposit due at signing, 40% on rough-in / mid-project milestone, 10% on substantial completion

Legal notes

  • · Projects over 4 months are subject to state-specific long-form contract disclosures; attorney review recommended before signing.

Ready to send this one?

Use this template kicks you into the ProJobCalc proposal builder with the scope, exclusions, payment terms, and variables pre-loaded.

Use this template