Pool Resurface & Remodel

Replaster, new tile, coping, and equipment upgrade on existing pool

Pool remodel covering replaster of interior surface (plaster, pebble, or aggregate), waterline tile replacement, coping replacement, and equipment-pad upgrade. Priced for 14,000–22,000 gallon residential pools at $9,500–$28,500.

Sections

10

Variables

14

Word count

~1500

Validity

30 days

Variables you'll fill in

{{client_name}}

Client namereq

e.g. Jane Homeowner

{{client_address}}

Project addressreq

e.g. 1234 Main St, Phoenix AZ 85001

{{contractor_name}}

Your company namereq

e.g. Acme Construction LLC

{{contractor_license}}

License numberreq

e.g. ROC 123456

{{scope_summary}}

One-paragraph scope summaryreq

e.g. Describe what this project covers in 2-3 sentences.

{{total}}

Total contract pricereq

e.g. 24500

{{deposit}}

Deposit / down paymentreq

e.g. 5000

{{start_date}}

Estimated start datereq

e.g. 2026-05-01

{{completion_date}}

Estimated substantial completionreq

e.g. 2026-06-15

{{proposal_date}}

Date of proposalreq

e.g. 2026-04-18

{{pool_gallons}}

Pool gallonsreq

e.g. 18000

{{interior_finish}}

New interior finishreq

e.g. Pebble Tec — Tropical Breeze

{{tile_selection}}

Waterline tile selectionreq

e.g. NPT Artistry — Iridescent Blue 6x6

{{coping_selection}}

Coping selectionreq

e.g. Travertine bullnose, 12" straight

Section-by-section preview

01Scope of Work

reqai rewritable

This proposal covers a remodel of the pool at {{client_address}} — approximately {{pool_gallons}} gallons. Scope includes:


Drain & prep

Drain pool via submersible pumps (to approved discharge)

Pressure wash interior surfaces

Install drain caps over hydrostatic valves to prevent pop-out during work


Demo

Chip existing plaster to concrete shell (hammer or bush-hammer; full chip-out, not bond coat)

Remove existing waterline tile

Remove existing coping (if being replaced)

Haul-off debris


Tile install

Install {{tile_selection}} at waterline; thinset with modified acrylic

Grout with color-matched sanded grout

Seal grout


Coping install

Install {{coping_selection}} coping on bond beam; mortar-set

Caulk expansion joint between coping and deck with self-leveling pool caulk

Miter and blend inside corners where visible


Interior resurface

Install acid-etched bond coat on shell

Install {{interior_finish}} — 3/8" thickness for plaster, 1/2" for pebble/aggregate

Hand-trowel or exposed-aggregate finish per product

Water pool immediately upon finish completion to begin startup cycle


Equipment pad (if in scope)

Replace pump, filter, heater, or salt system per itemized line items

Install new VSP (variable-speed pump) required by Energy Star in many states


Startup

Fill pool from house hose or water-truck (trucked fill itemized if needed)

Brush interior 2–3x daily during the first 30 days (plaster cure)

Balance water chemistry

Homeowner orientation on new plaster care (30-day brush schedule, startup chemistry)

02Schedule

reqai rewritable

Estimated duration: 2–4 weeks depending on weather and material lead times.


**Week 1:** Drain, demo, tile and coping install

**Week 2:** Interior finish, fill, startup

**Weeks 3–4:** 30-day plaster cure (daily brushing required — by homeowner or service company)


Start date: {{start_date}}. Pool is out of service for 2–3 weeks.

03Investment

req

Total contract price: {{total}}


**Deposit: {{deposit}}** — signing

**Demo complete: 30%**

**Tile and coping complete: 25%**

**Interior finish complete: 30%**

**Final: remainder** — at fill, startup, and walkthrough

04Payment Terms

req

Draws invoiced at milestone; due within 5 business days.


Invoices are due upon receipt. Payments more than ten (10) calendar days past due accrue a service charge of one and one-half percent (1.5%) per month on the unpaid balance, or the maximum rate permitted by law, whichever is less. {{contractor_name}} reserves the right to stop work and preserve lien rights if any progress payment is not received within five (5) business days of the due date. All retained mechanic's lien, stop notice, and bond rights under applicable state law are preserved.

05Exclusions

reqai rewritable

The following items are specifically NOT included in the contract price and are the responsibility of {{client_name}} unless added by written Change Order:


Permits, plan-review fees, and jurisdictional inspection fees unless explicitly itemized above

Repair or remediation of pre-existing code violations discovered during the work

Asbestos, lead paint, mold, or other hazardous material abatement

Structural engineering, architectural drawings, or third-party design services

Finish selections, fixtures, or appliances not listed in the itemized scope

Work on concealed systems (electrical, plumbing, HVAC, framing) beyond the points of connection identified

Landscaping restoration beyond returning disturbed areas to rough grade

Post-completion cleaning beyond construction broom-clean

Structural shell repair beyond minor crack patching (epoxy injection priced separately if needed)

Deck replacement or deck repair

Plumbing repair inside shell (pop-off returns, main drain grates priced separately unless itemized)

Electrical upgrades to equipment pad (GFCI panel, bonding grid upgrade)

Autofill replacement

Pool heater if not specifically itemized

Automation system (Pentair IntelliCenter, Jandy iAqualink) unless itemized

Water-truck fill costs if homeowner cannot fill from hose (billed at $250–$600 per truckload)

06Assumptions

reqai rewritable

This proposal is based on the following assumptions. If any assumption is incorrect, the contract price and schedule are subject to adjustment by Change Order:


Site access is available during normal working hours (7am–5pm, Monday–Saturday)

Adequate parking is available within 100 feet of the work area

Electrical power and potable water are available on-site at no cost to contractor

Existing structural elements, waste lines, water supply, and electrical service are in serviceable condition unless noted

{{client_name}} will remove personal property, artwork, and valuables from the work area prior to start

Work is based on a single mobilization; re-mobilization required due to delays outside contractor's control will be billed at current rates

Pool shell is structurally sound; no major cracks or rebar exposure

Existing pool plumbing is in serviceable condition

{{client_name}} agrees to brush plaster daily for the first 30 days after startup (or hire a service to do so)

Water table is below pool shell elevation (high water table requires dewatering, priced separately)

07Change Order Process

req

Any modification to the scope, specifications, materials, or schedule set forth in this agreement must be authorized in writing as a Change Order signed by both parties before the work is performed. Each Change Order will describe the modified scope, any adjustment to the contract price, and any impact on the schedule. Verbal instructions do not modify this agreement. Additional time and cost associated with unforeseen conditions — including but not limited to concealed rot, asbestos, mold, faulty prior installation, unmarked utilities, or code-required upgrades triggered by the work — will be documented as a Change Order and billed at the rates stated in this proposal or at {{contractor_name}}'s then-current published labor rates, whichever is in effect at the time the condition is discovered.

08Warranty

reqai rewritable

{{contractor_name}} warrants the workmanship of the installed work for a period of one (1) year from the date of substantial completion. Manufacturer warranties on materials and equipment pass through to {{client_name}} as provided by the manufacturer and are the exclusive source of any material warranty. This warranty does not cover normal wear, abuse, neglect, acts of God, subsequent work performed by others, damage from settlement or movement of the building, or modifications to the installed work performed without written consent. To make a warranty claim, {{client_name}} must notify {{contractor_name}} in writing within thirty (30) days of discovering the alleged defect and allow reasonable access to inspect and repair.

09Validity & Acceptance

req

This proposal is valid for 30 days from the proposal date ({{proposal_date}}). Pricing is subject to change after that date due to material market fluctuations and scheduling availability. Acceptance requires signature below and receipt of the deposit amount stated in Payment Terms. Upon acceptance, this proposal, together with any attached specifications and subsequent written Change Orders, constitutes the complete agreement between the parties and supersedes any prior oral or written discussions.

10Signatures

req

**{{contractor_name}}** — License {{contractor_license}}


By: ________________________ Date: ______________


Print Name: ________________________



**{{client_name}}** — Owner / Authorized Representative


By: ________________________ Date: ______________


Print Name: ________________________


Property Address: {{client_address}}

Default payment terms

50% deposit due at signing, 40% on rough-in / mid-project milestone, 10% on substantial completion

Legal notes

  • · Plaster/Pebble warranty: typically 1 year for plaster, 10 years prorated for pebble finishes (per manufacturer; registered at completion).
  • · Plaster cracking (hairline) can occur due to curing and is not a warranty defect unless structural.
  • · {{contractor_name}} is licensed per state pool contractor statute; license number on signature page.