Commercial Tenant Improvement

Build-out for leased retail, office, or restaurant space

Tenant improvement build-out for commercial leased space. Covers demolition, framing, drywall, flooring, finishes, electrical, plumbing, and HVAC modifications. Priced for 1,500–8,000 sq ft TI projects.

Sections

10

Variables

13

Word count

~1900

Validity

45 days

Variables you'll fill in

{{client_name}}

Client namereq

e.g. Jane Homeowner

{{client_address}}

Project addressreq

e.g. 1234 Main St, Phoenix AZ 85001

{{contractor_name}}

Your company namereq

e.g. Acme Construction LLC

{{contractor_license}}

License numberreq

e.g. ROC 123456

{{scope_summary}}

One-paragraph scope summaryreq

e.g. Describe what this project covers in 2-3 sentences.

{{total}}

Total contract pricereq

e.g. 24500

{{deposit}}

Deposit / down paymentreq

e.g. 5000

{{start_date}}

Estimated start datereq

e.g. 2026-05-01

{{completion_date}}

Estimated substantial completionreq

e.g. 2026-06-15

{{proposal_date}}

Date of proposalreq

e.g. 2026-04-18

{{space_sqft}}

Leased space square footagereq

e.g. 3200

{{space_type}}

Space type & usereq

e.g. Retail — specialty food; Type V-B construction; B occupancy

{{landlord_work_letter}}

Landlord work letter reference

e.g. Exhibit D, dated 2026-03-01

Section-by-section preview

01Scope of Work

reqai rewritable

This proposal covers tenant improvement build-out at {{client_address}} — {{space_sqft}} sq ft, use: {{space_type}}. Scope per approved TI plans and landlord work letter {{landlord_work_letter}}.


Demolition & prep

Remove non-structural partitions, existing flooring, ceiling tiles, and utilities not in scope

Dust walls and floor protection to adjacent tenant spaces

Coordinate building manager for after-hours noisy work (if required)


Framing & drywall

Metal stud partition walls per plans; fire-rated assemblies where required

Drywall, tape, and texture to match existing or per spec

Ceiling grid modifications; new ACT tile install


Mechanicals

Electrical: new circuits, panels, lighting, emergency lighting, exit signs per code

Plumbing: restroom modifications, break room sink, grease trap (if restaurant)

HVAC: ductwork modifications, new diffusers, VAV reconfiguration; commissioning

Fire sprinkler relocation/addition per shop drawings by licensed fire sub

Low-voltage rough-in: data, phone, A/V per IT requirements


Finishes

Flooring: VCT, LVT, carpet tile, or polished concrete per plan

Paint all walls per color schedule

Millwork: reception desk, built-ins, casework per plan

Storefront glass, interior glass walls (if applicable)

Signage coordination (signage by others unless included)


Closeout

Final inspections: building, electrical, plumbing, mechanical, fire, health dept (if applicable)

Certificate of Occupancy

As-built drawings delivered to landlord

Final clean

02Schedule

reqai rewritable

Estimated duration: 8–14 weeks from permit issuance to CoO, depending on scope complexity and jurisdictional turnaround.


**Critical path items:** Permit plan review (3–6 weeks typical), long-lead mechanical equipment, health department review (for food service). Project schedule is re-baselined at permit issuance.


Start date: on or about {{start_date}}. Target completion: {{completion_date}}.

03Investment

req

Total contract price: {{total}}


Fixed-price. Draw schedule follows AIA G702/G703 format with monthly invoicing for percentage-complete:


**Deposit: {{deposit}}** — signing (covers permit, mobilization, long-lead orders)

**Monthly progress draws** — invoiced the last business day of each month based on percentage-complete schedule of values

**10% retention** withheld from each draw; released upon CoO and punch list sign-off

**Final draw** — after CoO, punch completion, and submission of close-out documents (as-builts, O&M manuals, warranty package)

04Payment Terms

req

Monthly AIA-format billing, net 30. Retention of 10% held until CoO and close-out. {{contractor_name}} provides conditional lien waivers with each invoice and unconditional waivers upon payment. For tenant-paid portions, {{client_name}} may not set off landlord-tenant disputes against amounts owed under this contract.


Invoices are due upon receipt. Payments more than ten (10) calendar days past due accrue a service charge of one and one-half percent (1.5%) per month on the unpaid balance, or the maximum rate permitted by law, whichever is less. {{contractor_name}} reserves the right to stop work and preserve lien rights if any progress payment is not received within five (5) business days of the due date. All retained mechanic's lien, stop notice, and bond rights under applicable state law are preserved.

05Exclusions

reqai rewritable

The following items are specifically NOT included in the contract price and are the responsibility of {{client_name}} unless added by written Change Order:


Permits, plan-review fees, and jurisdictional inspection fees unless explicitly itemized above

Repair or remediation of pre-existing code violations discovered during the work

Asbestos, lead paint, mold, or other hazardous material abatement

Structural engineering, architectural drawings, or third-party design services

Finish selections, fixtures, or appliances not listed in the itemized scope

Work on concealed systems (electrical, plumbing, HVAC, framing) beyond the points of connection identified

Landscaping restoration beyond returning disturbed areas to rough grade

Post-completion cleaning beyond construction broom-clean

Landlord-provided items per work letter (typically shell, ADA path-of-travel, base building systems)

Tenant-supplied FF&E (furniture, fixtures, equipment)

Signage design, fabrication, and installation

POS, A/V, security, or IT equipment beyond low-voltage rough-in

Business license and health department fees

Commercial kitchen equipment (for restaurant TIs) unless separately contracted

06Assumptions

reqai rewritable

This proposal is based on the following assumptions. If any assumption is incorrect, the contract price and schedule are subject to adjustment by Change Order:


Site access is available during normal working hours (7am–5pm, Monday–Saturday)

Adequate parking is available within 100 feet of the work area

Electrical power and potable water are available on-site at no cost to contractor

Existing structural elements, waste lines, water supply, and electrical service are in serviceable condition unless noted

{{client_name}} will remove personal property, artwork, and valuables from the work area prior to start

Work is based on a single mobilization; re-mobilization required due to delays outside contractor's control will be billed at current rates

Landlord approves plans and authorizes access within 10 business days of submission

Building-standard materials are specified; tenant upgrades priced by Change Order

After-hours work is budgeted for 1 weekend day; additional after-hours requests billed at premium rates

07Change Order Process

req

Any modification to the scope, specifications, materials, or schedule set forth in this agreement must be authorized in writing as a Change Order signed by both parties before the work is performed. Each Change Order will describe the modified scope, any adjustment to the contract price, and any impact on the schedule. Verbal instructions do not modify this agreement. Additional time and cost associated with unforeseen conditions — including but not limited to concealed rot, asbestos, mold, faulty prior installation, unmarked utilities, or code-required upgrades triggered by the work — will be documented as a Change Order and billed at the rates stated in this proposal or at {{contractor_name}}'s then-current published labor rates, whichever is in effect at the time the condition is discovered.

08Warranty

reqai rewritable

{{contractor_name}} warrants the workmanship of the installed work for a period of one (1) year from the date of substantial completion. Manufacturer warranties on materials and equipment pass through to {{client_name}} as provided by the manufacturer and are the exclusive source of any material warranty. This warranty does not cover normal wear, abuse, neglect, acts of God, subsequent work performed by others, damage from settlement or movement of the building, or modifications to the installed work performed without written consent. To make a warranty claim, {{client_name}} must notify {{contractor_name}} in writing within thirty (30) days of discovering the alleged defect and allow reasonable access to inspect and repair.

09Validity & Acceptance

req

This proposal is valid for 45 days from the proposal date ({{proposal_date}}). Pricing is subject to change after that date due to material market fluctuations and scheduling availability. Acceptance requires signature below and receipt of the deposit amount stated in Payment Terms. Upon acceptance, this proposal, together with any attached specifications and subsequent written Change Orders, constitutes the complete agreement between the parties and supersedes any prior oral or written discussions.

10Signatures

req

**{{contractor_name}}** — License {{contractor_license}}


By: ________________________ Date: ______________


Print Name: ________________________



**{{client_name}}** — Owner / Authorized Representative


By: ________________________ Date: ______________


Print Name: ________________________


Property Address: {{client_address}}

Default payment terms

50% deposit due at signing, 40% on rough-in / mid-project milestone, 10% on substantial completion

Legal notes

  • · This template assumes a standard commercial lease with a tenant improvement allowance. Allowance reconciliation and landlord disbursement mechanics are documented separately.
  • · Payment bond and performance bond can be provided at {{client_name}} cost if required by landlord.