ADU — New Construction

Detached or attached accessory dwelling unit, foundation-to-finish

Ground-up construction of a permitted accessory dwelling unit. Includes foundation, framing, mechanicals, exterior envelope, and interior finish. Priced for 600–1,200 sq ft ADUs in the $185k–$395k range depending on jurisdiction and finish tier.

Sections

10

Variables

13

Word count

~2100

Validity

30 days

Variables you'll fill in

{{client_name}}

Client namereq

e.g. Jane Homeowner

{{client_address}}

Project addressreq

e.g. 1234 Main St, Phoenix AZ 85001

{{contractor_name}}

Your company namereq

e.g. Acme Construction LLC

{{contractor_license}}

License numberreq

e.g. ROC 123456

{{scope_summary}}

One-paragraph scope summaryreq

e.g. Describe what this project covers in 2-3 sentences.

{{total}}

Total contract pricereq

e.g. 24500

{{deposit}}

Deposit / down paymentreq

e.g. 5000

{{start_date}}

Estimated start datereq

e.g. 2026-05-01

{{completion_date}}

Estimated substantial completionreq

e.g. 2026-06-15

{{proposal_date}}

Date of proposalreq

e.g. 2026-04-18

{{adu_sqft}}

ADU square footagereq

e.g. 720

{{adu_type}}

ADU typereq

e.g. Detached new-build / Attached addition / Garage conversion

{{utility_plan}}

Utility plan

e.g. New 200A subpanel from main service; shared water; separate sewer lateral

Section-by-section preview

01Scope of Work

reqai rewritable

This proposal covers the construction of a {{adu_sqft}} sq ft {{adu_type}} ADU at {{client_address}}. Scope includes:


Site prep & foundation

Site survey review, stakeout, and rough grading for building pad

Excavation for footings and foundation stem walls

Concrete footings, stem walls, and slab-on-grade per structural plans

Perimeter drainage and moisture barrier


Framing & envelope

Framing of walls, floors (if two-story), and roof per approved structural plans

Roof sheathing, underlayment, and finish roofing (asphalt shingle or flat TPO depending on design)

Exterior wall sheathing, weather-resistive barrier, and siding (fiber cement or stucco per plans)

Windows and exterior doors per schedule


Mechanicals

{{utility_plan}}

Rough plumbing: DWV system, supply lines, water heater location, laundry connections

Rough electrical: panel/subpanel, branch circuits, dedicated circuits per NEC

Mini-split heat pump or central HVAC system with ductwork per design

Low-voltage rough-in (internet drop, smoke/CO detectors per code)


Interior finish

Insulation (code-minimum or upgraded per plans)

Drywall, texture, and paint

Flooring throughout (LVP, tile, or hardwood per selection)

Kitchen cabinets, counter, sink, and basic appliance package (range, refrigerator, dishwasher)

Bathroom(s): tub/shower, vanity, toilet, tile surround

Interior doors, trim, closet shelving

Light fixtures and plumbing trim


Closeout

Final inspections with AHJ (electrical, plumbing, mechanical, building final)

Certificate of Occupancy or final jurisdictional approval

Walk-through and punch list

02Schedule

reqai rewritable

Estimated duration: 5–7 months from permit issuance to Certificate of Occupancy.


**Month 1:** Site prep, excavation, foundation, foundation inspection

**Month 2:** Framing, roofing, window install, framing inspection

**Month 3:** Rough mechanicals, mechanical inspections, insulation

**Month 4:** Drywall, paint prep, exterior finish

**Month 5:** Flooring, cabinets, tile, trim, fixtures

**Month 6:** Punch list, final inspections, CoO


Jurisdictional delays (permit review, inspection backlog, utility connection timing) can add 30–90 days to the critical path. Start date: {{start_date}}. Target substantial completion: {{completion_date}}.

03Investment

req

Total contract price: {{total}}


Fixed-price with a progress draw schedule:


**Deposit: {{deposit}}** — signing; covers plans, permit applications, and site mobilization

**Foundation: 15%** — upon passing foundation inspection

**Framing/Dry-in: 20%** — upon passing framing inspection; building weather-tight

**Mechanicals rough: 15%** — upon passing all rough mechanical inspections

**Insulation/Drywall: 10%** — upon drywall tape and texture completion

**Finish installation: 15%** — upon cabinet, counter, tile, and flooring completion

**Substantial completion: remaining balance** — upon CoO and punch list sign-off

04Payment Terms

req

Draws invoiced at milestone achievement, due within 7 business days. Unconditional lien waivers provided at each draw upon payment clearance.


Invoices are due upon receipt. Payments more than ten (10) calendar days past due accrue a service charge of one and one-half percent (1.5%) per month on the unpaid balance, or the maximum rate permitted by law, whichever is less. {{contractor_name}} reserves the right to stop work and preserve lien rights if any progress payment is not received within five (5) business days of the due date. All retained mechanic's lien, stop notice, and bond rights under applicable state law are preserved.

05Exclusions

reqai rewritable

The following items are specifically NOT included in the contract price and are the responsibility of {{client_name}} unless added by written Change Order:


Permits, plan-review fees, and jurisdictional inspection fees unless explicitly itemized above

Repair or remediation of pre-existing code violations discovered during the work

Asbestos, lead paint, mold, or other hazardous material abatement

Structural engineering, architectural drawings, or third-party design services

Finish selections, fixtures, or appliances not listed in the itemized scope

Work on concealed systems (electrical, plumbing, HVAC, framing) beyond the points of connection identified

Landscaping restoration beyond returning disturbed areas to rough grade

Post-completion cleaning beyond construction broom-clean

Design and engineering fees (architectural plans, structural stamps) unless separately contracted with {{contractor_name}}

Utility connection fees, capacity charges, or impact fees levied by the jurisdiction

Driveway extension, walkways, or landscaping beyond rough grade

Solar PV installation

Appliance upgrades beyond the base package

Furnishings, window treatments

06Assumptions

reqai rewritable

This proposal is based on the following assumptions. If any assumption is incorrect, the contract price and schedule are subject to adjustment by Change Order:


Site access is available during normal working hours (7am–5pm, Monday–Saturday)

Adequate parking is available within 100 feet of the work area

Electrical power and potable water are available on-site at no cost to contractor

Existing structural elements, waste lines, water supply, and electrical service are in serviceable condition unless noted

{{client_name}} will remove personal property, artwork, and valuables from the work area prior to start

Work is based on a single mobilization; re-mobilization required due to delays outside contractor's control will be billed at current rates

Site is zoned for ADU and all setback requirements are met on approved plans

Soil conditions are suitable for a conventional slab-on-grade foundation (geotechnical report if required is separately contracted)

Utility service capacity exists at the meter; major service upgrades priced separately

07Change Order Process

req

Any modification to the scope, specifications, materials, or schedule set forth in this agreement must be authorized in writing as a Change Order signed by both parties before the work is performed. Each Change Order will describe the modified scope, any adjustment to the contract price, and any impact on the schedule. Verbal instructions do not modify this agreement. Additional time and cost associated with unforeseen conditions — including but not limited to concealed rot, asbestos, mold, faulty prior installation, unmarked utilities, or code-required upgrades triggered by the work — will be documented as a Change Order and billed at the rates stated in this proposal or at {{contractor_name}}'s then-current published labor rates, whichever is in effect at the time the condition is discovered.

08Warranty

reqai rewritable

{{contractor_name}} warrants the workmanship of the installed work for a period of one (1) year from the date of substantial completion. Manufacturer warranties on materials and equipment pass through to {{client_name}} as provided by the manufacturer and are the exclusive source of any material warranty. This warranty does not cover normal wear, abuse, neglect, acts of God, subsequent work performed by others, damage from settlement or movement of the building, or modifications to the installed work performed without written consent. To make a warranty claim, {{client_name}} must notify {{contractor_name}} in writing within thirty (30) days of discovering the alleged defect and allow reasonable access to inspect and repair.

09Validity & Acceptance

req

This proposal is valid for 30 days from the proposal date ({{proposal_date}}). Pricing is subject to change after that date due to material market fluctuations and scheduling availability. Acceptance requires signature below and receipt of the deposit amount stated in Payment Terms. Upon acceptance, this proposal, together with any attached specifications and subsequent written Change Orders, constitutes the complete agreement between the parties and supersedes any prior oral or written discussions.

10Signatures

req

**{{contractor_name}}** — License {{contractor_license}}


By: ________________________ Date: ______________


Print Name: ________________________



**{{client_name}}** — Owner / Authorized Representative


By: ________________________ Date: ______________


Print Name: ________________________


Property Address: {{client_address}}

Default payment terms

50% deposit due at signing, 40% on rough-in / mid-project milestone, 10% on substantial completion

Legal notes

  • · ADU rental regulations vary by jurisdiction; {{client_name}} is responsible for short-term rental compliance and any HOA restrictions.
  • · Consult tax advisor regarding property tax reassessment implications.