Full Bathroom Remodel

Complete bathroom renovation including demo, waterproofing, tile, fixtures, and vanity

Full bathroom remodel for a residential bath — demo existing finishes, rough plumbing/electrical, waterproofing, tile shower and floor, new vanity, toilet, fixtures, mirrors, and accessories. Priced for 40–120 sq ft baths in the $12k–$45k range depending on finish tier and layout complexity.

Sections

10

Variables

15

Word count

~1600

Validity

30 days

Variables you'll fill in

{{client_name}}

Client namereq

e.g. Jane Homeowner

{{client_address}}

Project addressreq

e.g. 1234 Main St, Phoenix AZ 85001

{{contractor_name}}

Your company namereq

e.g. Acme Construction LLC

{{contractor_license}}

License numberreq

e.g. ROC 123456

{{scope_summary}}

One-paragraph scope summaryreq

e.g. Describe what this project covers in 2-3 sentences.

{{total}}

Total contract pricereq

e.g. 24500

{{deposit}}

Deposit / down paymentreq

e.g. 5000

{{start_date}}

Estimated start datereq

e.g. 2026-05-01

{{completion_date}}

Estimated substantial completionreq

e.g. 2026-06-15

{{proposal_date}}

Date of proposalreq

e.g. 2026-04-18

{{bath_sqft}}

Bathroom square footagereq

e.g. 65

{{shower_type}}

Shower typereq

e.g. Walk-in tile shower with frameless glass enclosure

{{vanity_scope}}

Vanity scopereq

e.g. 48" double-sink floating vanity — owner-supplied

{{tile_selections}}

Tile selectionsreq

e.g. 12×24 porcelain floor tile; 4×16 subway shower wall tile — owner-supplied

{{layout_changes}}

Layout changes

e.g. None — fixture locations unchanged

Section-by-section preview

01Scope of Work

reqai rewritable

This proposal covers a complete renovation of the bathroom at {{client_address}} — approximately {{bath_sqft}} sq ft.


Phase 1 — Demo & rough-in

Demo and haul-off of existing tile, drywall, vanity, toilet, tub/shower surround, and fixtures

Remove existing plumbing fixtures (shutoff valves, p-traps, supply lines) and cap for rough-in

Rough plumbing: relocate or extend supply/drain as needed for new layout ({{layout_changes}})

Rough electrical: GFCI-protected circuits at vanity and shower zones per NEC; exhaust fan circuit

Install cement board or waterproof backer on all wet-zone walls to shower curb height +6 inches

Apply waterproof membrane (Schluter Kerdi or equal) to shower floor and pan; flood test prior to tile


Phase 2 — Tile & shower

Install {{shower_type}}

Install tile per selections: {{tile_selections}}

All grout joints filled and sealed; silicone at all inside corners and transitions per tile industry standards (TCNA)

Install shower valve body, integral diverter where applicable; temperature limit stop set per code

Install shower niche(s) per plan (one standard 12×24 niche included; additional by Change Order)


Phase 3 — Vanity, fixtures & finish work

Install {{vanity_scope}}

Install countertop and undermount sink(s) (template and cutout included)

Finish plumbing: faucet, p-trap, shutoff valves, drain

Install toilet (owner-supplied or standard contractor-supplied — noted in Pricing)

Install exhaust fan (owner-supplied or standard — noted in Pricing)

Install vanity light, mirror, and accessories per selections

Paint walls and ceiling (color per owner selections)

Install door hardware if replaced


Phase 4 — Punch & closeout

Caulk and grout touch-up

Walk-through with {{client_name}}; punchlist completed within 5 business days

Final clean including inside of vanity cabinet

02Schedule

reqai rewritable

Estimated project duration: 3–5 weeks from start date, depending on tile lead time and material selection timing.


**Week 1:** Demo, rough plumbing, rough electrical, cement board and waterproofing

**Week 2:** Flood test, tile shower floor and walls

**Week 3:** Floor tile, grouting, glass enclosure templating

**Week 4:** Vanity installation, finish plumbing, fixtures

**Week 5:** Glass installation, accessories, punch, final clean


Start date: on or about {{start_date}}. Schedule assumes all tile and fixture selections are finalized and on-site at least 7 days before start. Frameless glass lead time is typically 10–18 business days after template.

03Investment

req

Total contract price: {{total}}


Fixed-price contract based on selections documented at signing. Substitutions after material order may result in a Change Order.


Payment schedule:

**Deposit: {{deposit}}** — at signing; reserves crew and authorizes material order

**Rough-in milestone:** upon completion of demo, rough plumbing, electrical, and waterproofing (typically end of Week 1)

**Tile milestone:** upon completion of shower tile and floor tile (typically end of Week 3)

**Balance:** upon substantial completion and client walk-through approval


NOTE: Glass enclosure is measured and templated after tile is complete — any change to shower opening dimensions after template is subject to restocking fees from the glass fabricator.

04Payment Terms

req

Deposit at signing (reserves crew and authorizes material orders); milestone payments at rough-in completion and tile completion; balance on substantial completion. Payment due within 5 business days of each milestone invoice.


Invoices are due upon receipt. Payments more than ten (10) calendar days past due accrue a service charge of one and one-half percent (1.5%) per month on the unpaid balance, or the maximum rate permitted by law, whichever is less. {{contractor_name}} reserves the right to stop work and preserve lien rights if any progress payment is not received within five (5) business days of the due date. All retained mechanic's lien, stop notice, and bond rights under applicable state law are preserved.

05Exclusions

reqai rewritable

The following items are specifically NOT included in the contract price and are the responsibility of {{client_name}} unless added by written Change Order:


Permits, plan-review fees, and jurisdictional inspection fees unless explicitly itemized above

Repair or remediation of pre-existing code violations discovered during the work

Asbestos, lead paint, mold, or other hazardous material abatement

Structural engineering, architectural drawings, or third-party design services

Finish selections, fixtures, or appliances not listed in the itemized scope

Work on concealed systems (electrical, plumbing, HVAC, framing) beyond the points of connection identified

Landscaping restoration beyond returning disturbed areas to rough grade

Post-completion cleaning beyond construction broom-clean

Structural modifications to walls or floor joists (quoted separately; may require engineer review)

Permit fees (included in total where required; owner reimburses if cost changes after permit application)

Radiant floor heat (rough wiring only if panel capacity exists; system and controls by Change Order)

Steam shower generator or specialty shower systems beyond standard valve and diverter

Asbestos or lead-paint abatement (pre-1978 homes may require testing; abatement by licensed sub, billed separately)

Window replacement or exterior modifications

Mold remediation beyond normal surface cleaning (encapsulation by licensed sub if discovered)

06Assumptions

reqai rewritable

This proposal is based on the following assumptions. If any assumption is incorrect, the contract price and schedule are subject to adjustment by Change Order:


Site access is available during normal working hours (7am–5pm, Monday–Saturday)

Adequate parking is available within 100 feet of the work area

Electrical power and potable water are available on-site at no cost to contractor

Existing structural elements, waste lines, water supply, and electrical service are in serviceable condition unless noted

{{client_name}} will remove personal property, artwork, and valuables from the work area prior to start

Work is based on a single mobilization; re-mobilization required due to delays outside contractor's control will be billed at current rates

All tile, fixtures, vanity, and accessories are owner-supplied to site at least 7 days before start, or contractor-supplied as noted in Pricing

Existing drain stack, vent, and water supply are accessible and code-compliant; corroded supply lines replaced at T&M

Existing electrical panel has capacity for GFCI circuits and exhaust fan; panel upgrade not included

Floor joists are structurally sound and level within 3/16 in. over 10 ft; additional leveling compound at T&M if warranted

No hidden mold, asbestos, or structural damage beyond normal renovation conditions

Owner is responsible for removing personal property from bathroom before start date

Frameless glass lead time is accounted for in schedule; owner to approve shop drawing within 48 hours of template

07Change Order Process

req

Any modification to the scope, specifications, materials, or schedule set forth in this agreement must be authorized in writing as a Change Order signed by both parties before the work is performed. Each Change Order will describe the modified scope, any adjustment to the contract price, and any impact on the schedule. Verbal instructions do not modify this agreement. Additional time and cost associated with unforeseen conditions — including but not limited to concealed rot, asbestos, mold, faulty prior installation, unmarked utilities, or code-required upgrades triggered by the work — will be documented as a Change Order and billed at the rates stated in this proposal or at {{contractor_name}}'s then-current published labor rates, whichever is in effect at the time the condition is discovered.

08Warranty

reqai rewritable

{{contractor_name}} warrants the workmanship of the installed work for a period of one (1) year from the date of substantial completion. Manufacturer warranties on materials and equipment pass through to {{client_name}} as provided by the manufacturer and are the exclusive source of any material warranty. This warranty does not cover normal wear, abuse, neglect, acts of God, subsequent work performed by others, damage from settlement or movement of the building, or modifications to the installed work performed without written consent. To make a warranty claim, {{client_name}} must notify {{contractor_name}} in writing within thirty (30) days of discovering the alleged defect and allow reasonable access to inspect and repair.

09Validity & Acceptance

req

This proposal is valid for 30 days from the proposal date ({{proposal_date}}). Pricing is subject to change after that date due to material market fluctuations and scheduling availability. Acceptance requires signature below and receipt of the deposit amount stated in Payment Terms. Upon acceptance, this proposal, together with any attached specifications and subsequent written Change Orders, constitutes the complete agreement between the parties and supersedes any prior oral or written discussions.

10Signatures

req

**{{contractor_name}}** — License {{contractor_license}}


By: ________________________ Date: ______________


Print Name: ________________________



**{{client_name}}** — Owner / Authorized Representative


By: ________________________ Date: ______________


Print Name: ________________________


Property Address: {{client_address}}

Default payment terms

50% deposit due at signing, 40% on rough-in / mid-project milestone, 10% on substantial completion

Legal notes

  • · All trade work permitted where required by local jurisdiction. Permit copies provided at closeout.
  • · Tile and fixture warranties pass through to {{client_name}} from manufacturer; contractor provides 1-year workmanship warranty on installation.
  • · Waterproofing membrane warranty (typically 10 years from manufacturer) registered to {{client_name}} at closeout.